Plant/Process Description:
Town Becej is locate in north Serbia from 75km
to the Hungary. The construction of a modern
water supply system in Becej began in the late
70's. It consists of a central water source
outside the town, a central water treatment
plant and a water supply system distribution
network (reservoir and a pump station).
About 24.000 inhabitants are connected to the
public water supply network, that is 85% of the
population living in Becej. The average water
consumption (industrial and household) is 100
l/s and 150 l/s in summer period.
An important fact is that only a part of the
town industry uses the public water supply
network until other major plants and factories
have their own wells. From the sources of 13
active wells, the water exploitation is 100-110
l/s which doesn't satisfy the need of the town
that is 135 l/s Water treatment plant have
degasification (methane),filtration (iron),
2500m3 tank, pumping station (3*110kW-
Q=100l/s,H=65m 2*75kW-q=60l/s, H=65m) and
disinfection equipment (chlorine).
Waste Water Treatment Plant
The construction work on the wastewater
treatment plant began in 1972. Since Becej is a
town of Pannonian type, the ground configuration
allows no significant sewerage system level
differences and due to this fact the
construction of 7 pump stations is foreseen on
the sewerage system. The ground configuration
is on the other hand advantageous for the storm-
water sewerage system. The construction of 16
main storm-water sewers was planned but only 5
have been built.
The precipitation collectors are the backwaters
of the Tisa River and the Bezdan-Becej Canal.
The collected wastewater quantities from
households, industry and institutions are
diverted to the wastewater treatment plant that
was put into operation in 1989. The wastewater
treatment is based on biologically active mud.
The treated wastewater collector is the Bezdan-
Becej Canal. The construction of this
wastewater plant was conducted in phases,
depending on the incoming wastewater quantity
and quality. On the basis of constructed
facilities (1stphase ) the wastewater treatment
plant can be loaded up to next limits:
Hydraulic Q=7750m3/ day
Organic R=3000 kg BOC5/day
Equivalent population number 50,000
The water purification is up to 80-90%.
|