Biogas systems serve as the critical interface between anaerobic digestion processes and energy recovery or disposal mechanisms in municipal and industrial wastewater treatment facilities. While historically viewed merely as a waste byproduct requiring safe disposal, biogas—comprising primarily methane (CH4) and carbon dioxide (CO2)—is now universally recognized as a valuable renewable energy resource. The engineering design, specification, and OEM selection for biogas handling, conditioning, and safety equipment determine not only the safety of the facility but also the economic viability of Combined Heat and Power (CHP) or Renewable Natural Gas (RNG) initiatives.
In a typical Water Resource Recovery Facility (WRRF), the biogas system encompasses the piping, valves, safety devices, conditioning skids, and storage mechanisms located immediately downstream of the anaerobic digesters. The primary operational objectives are threefold: to maintain strictly controlled pressure within the digester headspace to prevent structural damage or oxygen intrusion; to safely convey gas to combustion devices (boilers, flares, engines); and to condition the gas by removing moisture, hydrogen sulfide (H2S), and siloxanes to protect downstream generation assets.
The regulatory environment governing these systems is rigorous. Engineers must design in strict accordance with standards such as NFPA 820 (Standard for Fire Protection in Wastewater Treatment and Collection Facilities), which dictates hazardous area classifications (Class 1, Division 1 or 2) based on ventilation and gas containment. Furthermore, environmental regulations regarding methane emissions and sulfur dioxide (SO2) limits from flaring necessitate high-efficiency destruction and thorough gas scrubbing.
OEM selection in this category is uniquely critical due to the volatile nature of the medium. Unlike liquid stream processes where failure results in a spill or permit violation, failure in biogas handling (such as a flame arrester failure or pressure relief valve malfunction) can lead to catastrophic deflagration, structural rupture of digester covers, or asphyxiation hazards. Consequently, equipment must be specified based on proven reliability, precise leak-rate tolerances, and robust materials of construction capable of withstanding the highly corrosive nature of raw biogas.
Selecting equipment for biogas systems requires a multi-disciplinary approach involving chemical, mechanical, and safety engineering principles. The “biogas system” is not a single unit but a train of components including safety relief valves, flame arresters, sediment traps, gas scrubbers, compressors, storage holders, and waste gas burners (flares). The following engineering criteria define the specification process.
The fundamental requirement is pressure management. Anaerobic digesters typically operate at very low pressures, often between 6 to 12 inches of water column (w.c.). Equipment selection begins with a rigorous hydraulic (pneumatic) profile of the gas train. The total backpressure exerted by the piping, flame arresters, and downstream utilization equipment must not exceed the operating pressure of the digester covers. OEMs must be evaluated on the pressure drop characteristics of their components. A flame arrester with a high pressure drop may necessitate larger piping diameters or booster blowers, significantly altering the capital and operational cost profile.
Performance also dictates the selection of safety devices. Vacuum relief is as critical as pressure relief; drawing a vacuum on a digester due to rapid sludge withdrawal or thermal contraction can collapse a steel or concrete cover. Relief valves must be sized based on API 2000 standards, accounting for maximum gas generation rates and emergency pump-out scenarios.
Biogas flow is rarely static. It fluctuates based on digestion kinetics, temperature changes, and feeding cycles. Equipment must be sized for peak instantaneous flow, not just average daily production. For gas conditioning systems, turndown ratio is a key specification. If a facility produces fluctuating gas volumes, the H2S removal system and moisture removal skids must maintain removal efficiencies across the full flow range. Engineers should specify positive displacement blowers or variable frequency drive (VFD) equipped centrifugal blowers that can match the digester gas production without creating dangerous negative pressure situations.
Raw biogas is a hostile environment. It is fully saturated with moisture and contains H2S, which forms sulfuric acid upon condensation, and CO2, which forms carbonic acid. Standard carbon steel is generally unsuitable for wetted parts unless heavily coated, which poses long-term maintenance risks. The industry standard specification is Stainless Steel 316L for all valve internals, flame arrester elements, and critical piping sections. For valve bodies and housings, aluminum may be used in lower-severity applications, but cast iron or stainless steel is preferred for durability. Diaphragms and seals must be composed of elastomers like PTFE (Teflon) or Viton that resist chemical attack and do not degrade under continuous exposure to methane and trace VOCs.
The biogas system acts as the bridge between the biology of the digester and the mechanics of the energy plant. Integration requires careful logic programming. For example, waste gas burners (flares) must automatically modulate to maintain digester pressure when the CHP engine trips offline. If the reaction time of the flare valve is too slow, the pressure relief valves on the digester roof may lift, venting methane to the atmosphere—a reportable environmental event and a safety hazard. Engineers must verify that the OEM’s instrumentation (pressure transmitters, flow meters) integrates seamlessly with the plant SCADA system to provide real-time balancing of gas flows.
Biogas safety equipment often requires specific installation distances to function correctly. For instance, deflagration flame arresters have a maximum “run-up” distance (the length of pipe between the ignition source and the arrester) typically limited to 50 pipe diameters or less. Exceeding this distance can allow a flame front to accelerate from a deflagration to a detonation, which most standard arresters cannot stop. Detonation arresters, which can handle supersonic flame fronts, are heavier, more expensive, and have higher pressure drops. Layout planning must prioritize placing safety equipment within certified distances, often necessitating rooftop installations or dedicated valve vaults that require classified electrical ratings.
While safety valves are passive, gas conditioning systems are active energy consumers. Gas cooling (chilling) to remove moisture requires significant refrigeration tonnage. Adsorption systems for siloxane removal impose pressure drops that increase blower horsepower requirements. When selecting gas cleaning OEMs, engineers should evaluate the lifecycle cost of media replacement. Activated carbon media for H2S removal is an expensive recurring operational cost. Biological scrubbers (bioscrubbers) offer lower operating costs but higher capital investment and more complex process control. The trade-off analysis should calculate the cost per cubic foot of treated gas over a 20-year horizon.
Maintenance access is frequently overlooked in biogas system design. Flame arrester elements are prone to fouling from biological foam, particulate matter, and sulfur deposits. If an arrester is installed 20 feet in the air without a service platform, it will not be cleaned, leading to blinding and eventual pressure relief activation. Engineers should specify “draw-out” or easy-access designs for arrester banks. Similarly, pressure/vacuum relief valves (PVRVs) require annual bench testing to verify set points. OEMs that offer pallet assemblies that can be easily removed or swapped in the field are preferred over units requiring complete removal from the pipe header.
The most common failure mode in biogas systems is valve seat leakage. Due to the low operating pressures, valves rely on the weight of the pallet or a light spring to seal. Even minor corrosion or debris on the seat can cause continuous leakage of fugitive methane (odors and revenue loss). Freezing is another critical failure mode in cold climates; condensate can freeze valve pallets shut, rendering safety devices useless. OEMs addressing this with heated valve jackets, non-stick seat materials, and superior condensate drainage designs demonstrate higher reliability.
Initial capital cost for biogas equipment is often a fraction of the lifecycle cost. Low-cost valves often require more frequent replacement of seals and pallets. Cheap flame arresters may corrode, requiring total unit replacement rather than simple element cleaning. The highest cost, however, is the risk cost. A catastrophic failure resulting in a digester roof rupture can cost millions in repairs and months of downtime. Therefore, premium OEMs with documented third-party verification of flow curves and leak rates typically offer the lowest risk-adjusted lifecycle cost.
The following table compares the leading OEMs for Biogas Systems. This comparison focuses on their primary areas of specialization within the biogas train—Safety/Handling, Conditioning/Cleaning, and Storage. Engineers should use this table to align specific project subsystems (e.g., flares vs. scrubbers) with the manufacturer best suited for that specific technology, rather than assuming a single vendor provides a comprehensive solution for all distinct unit processes.
| OEM Name | Typical Applications | Engineering Strengths | Limitations | Maintenance Considerations |
|---|---|---|---|---|
| Varec Biogas | Safety relief valves (PVRV), Flame arresters, Waste gas burners, Regulators. | Industry standard for durability; massive install base; modular valve designs allow easy repairs; highly accurate low-pressure control. | Primarily focused on handling/safety hardware; less focus on complex biological gas scrubbing technologies. | Simplified maintenance with replaceable seat rings and pallets; extensive spare parts availability through distribution. |
| Groth Corporation | Pressure/Vacuum relief valves, Deflagration/Detonation arresters, Pilot-operated valves. | Precision machining results in exceptionally low leak rates (bubble-tight); broad range of exotic materials for corrosive applications. | Product portfolio is heavily concentrated on valves and safety devices, requiring integration with other vendors for flares/scrubbing. | High-precision components require careful handling during service; cleaning of flame elements is straightforward but critical. |
| Shand & Jurs | Tank instrumentation, Insulation-jacketed valves, Water-sealed valves, Flares. | Excellent solutions for cold-weather climates (“All-Weather” designs); insulation jackets prevent freezing; robust “Expanda-Seal” technology. | Similar to Groth/Varec, focus is on the mechanical safety hardware rather than gas upgrading processes. | “Expanda-Seal” diaphragms provide tight sealing but require periodic inspection to ensure elasticity is maintained. |
| Evoqua (Xylem) | Gas cleaning (H2S removal), Odor control, Anaerobic Digester Covers, Geomembrane covers. | Comprehensive process solutions including biological and chemical scrubbing; strong expertise in digester cover integration. | Systems are often large, engineered packages rather than off-the-shelf components; higher capital intensity for full systems. | Media change-outs for scrubbers can be labor-intensive; biological systems require nutrient monitoring and biomass management. |
| WesTech Engineering | DuoSphere gasholders, Digester covers (steel and membrane), Gas safety integration. | Market leader in gas storage (double membrane spheres); integrates storage seamlessly with cover design and safety systems. | Primary focus is structural/storage (covers and holders) rather than standalone valve manufacturing or gas upgrading. | Membrane systems require periodic inspection for tears or UV degradation; blowers for air-ballast systems require standard maintenance. |
The following manufacturers represent the established tier of Original Equipment Manufacturers for biogas handling, safety, and conditioning. Selection should be based on the specific subsystem being designed (e.g., safety relief vs. gas storage) as capabilities vary significantly between these entities.
Varec Biogas is arguably the most recognizable name in the North American municipal wastewater biogas market. Their legacy dates back nearly a century, establishing the baseline standards for sewage gas handling.
Groth Corporation acts as a direct competitor to Varec in the safety valve and flame arrester market, often distinguishing itself through precision engineering and low-leakage performance.
Shand & Jurs (an L&J Technologies company) is another historical pillar of the tank gauging and safety valve industry. They have a particularly strong reputation for addressing environmental challenges such as freezing.
While the previous OEMs focus on valves and safety hardware, Evoqua (now part of Xylem) is a dominant force in gas conditioning, cleaning, and digester covers.
WesTech is primarily known for process equipment, but in the biogas sector, they are a market leader in gas storage and containment.
Selecting the right OEM requires matching the manufacturer’s strength to the facility’s specific needs. One manufacturer rarely provides the “best” solution for every component in the gas train.
For standard municipal plants, reliability and ease of maintenance are paramount. Varec Biogas is often the default choice for the “safety loop” (PVRVs, arresters) due to familiarity among operators and universal spare parts availability. If the plant is in a severe freeze zone, Shand & Jurs jacketed valves should be specified for outdoor rooftop installations. For gas storage, WesTech dual-membrane spheres are the modern standard, replacing older steel floating gas holders which are maintenance-intensive.
Industrial anaerobic systems (e.g., food and beverage, breweries) often produce biogas with significantly higher H2S concentrations than municipal sludge. Here, material compatibility is critical. Groth Corporation offers excellent material options (Hastelloy, etc.) for safety valves. For the cleaning of this sour gas, Evoqua’s biological scrubbers are highly recommended to handle the high sulfur loading without bankrupting the facility on media replacement costs.
RNG projects require the strictest gas quality and leakage control. The value of the gas is high, making fugitive emissions costly. Groth Corporation is often favored here for safety valves due to their superior seat tightness (10% of API 2000 allowable leakage). For the conditioning systems upstream of membrane separation, Evoqua or specialized gas train integrators are necessary to remove siloxanes to non-detectable levels.
In retrofit applications, footprint is a major constraint. Varec and Groth offer inline flame arresters and valves that can be easily swapped into existing piping galleries. For greenfield sites, engineers have the luxury of designing optimal spacing. This favors large-scale biological scrubbers from Evoqua and separate gas storage spheres from WesTech, rather than trying to store gas under the digester cover itself.
Beyond the catalog specifications, the long-term success of a biogas system relies on practical implementation strategies.
A critical oversight in biogas design is the failure to pressure-test the piping system before introducing gas. The system operates at such low pressures that standard hydrostatic testing is inappropriate; pneumatic testing with low-pressure air and soap solution on joints is required. Engineers must specify that safety relief valves are isolated or removed during pipe pressure testing, as test pressures often exceed the sensitive settings of the relief pallets, potentially damaging them before operation begins.
Flame arresters are passive devices, but they are not “install and forget.” The narrow crimped metal ribbons (the element) that stop flames act as excellent filters for particulate and grease. If they clog, digester pressure rises, lifting relief valves and venting odors. Operators must have safe access—platforms, not ladders—to remove these heavy elements for cleaning. Design the piping with “spool pieces” or jackscrews to allow for easy removal of the arrester element without springing the piping.
For critical safety valves, the “N+1” philosophy is challenging because you cannot simply install a standby relief valve on a digester roof (both must be active to handle emergency flows). Therefore, the spare parts strategy is vital. Facilities should stock a complete set of replacement pallets and flame arrester elements. Cleaning a flame arrester element can take hours of soaking in solvent; having a clean spare ready to swap in immediately reduces downtime from hours to minutes.
Biogas is 100% humid. As it cools in the piping, it drops significant water volume. Piping must always slope back to the digester or to dedicated drip traps (sediment traps). A common design error is installing a safety valve at a low point in the piping; condensate will accumulate on top of the valve pallet, artificially increasing the set pressure (water column weight) and preventing the valve from opening when needed. Always install safety devices at high points or ensure positive drainage away from the valve seat.
Specifying biogas systems is a high-stakes engineering task where the margin for error is measured in inches of water column. The selection of OEMs must prioritize safety and reliability above all else. For the foundational safety hardware—relief valves and flame arresters—Varec Biogas, Groth Corporation, and Shand & Jurs represent the industry triumvirate, each with distinct strengths in durability, precision, and weather resilience, respectively. For the increasing complexity of gas conditioning and storage, Evoqua and WesTech provide the process-heavy solutions required for modern energy recovery.
Engineers are advised to treat the biogas train not as a collection of pipes, but as a dynamic pressure vessel system. Success lies in calculating accurate pressure drops, selecting materials compatible with the sour gas environment, and ensuring that the selected equipment can be practically maintained by the operations staff who will inherit the system. By aligning the unique strengths of these top OEMs with the specific hydraulic and environmental constraints of the project, engineers can deliver biogas systems that are safe, compliant, and energy-positive.